How long floor screed takes to dry before the floor covering goes down

8 May 2026 · Стяжка.укр · 7 min read

The question we hear most once the screed is down: when can laminate, tiles or parquet go on? Rushing this is what ruins a floor a month or two later. Here are the real timings for each type of screed and each covering.

The rule of thumb

The classic rule for a cement-sand screed is 1 cm of thickness = 1 week of drying. So 5 cm needs five weeks and 7 cm nearly two months. That formula is for wet screed at around +20°C and up to 60% humidity.

The figure shifts with:

Semi-dry screed

A semi-dry machine-applied screed holds far less water than a classic wet one, so it dries faster:

Note: by day 4–7 the surface looks dry, but there is still water inside the layer. That is why tiles wait until day 7–14, and laminate or parquet until the moisture check.

Wet (classic) screed

Cement and sand with plenty of water in the mix. The timings are longer:

How to check it is ready

Method 1: a sheet of polythene

Tape a 1 × 1 m piece of polythene down onto the screed, sealing all four edges, and leave it for 24 hours. Droplets underneath mean the screed is still wet. A dry sheet means you can lay the covering.

Method 2: a moisture meter

The accurate way. Permissible residual moisture in the screed:

Method 3: by eye

The screed turns light grey (fresh screed is darker). It is the least reliable check though — use the polythene or a meter.

What happens if you lay the covering too early

What actually goes wrong:

How to speed drying up

In short: when you can lay

For a 5 cm semi-dry screed in normal conditions:

Why tiles can go down sooner. Drying all the way down to 2% takes longer — roughly a week per centimetre of thickness. But ceramic tile on cement adhesive tolerates residual moisture: it is vapour-permeable through the joints, so the last of the water escapes from under the finished floor. Laminate, parquet and vinyl cannot do that — the moisture is trapped, which is why they wait for the 2% check. Where the demands are higher (large format, epoxy adhesive, underfloor heating) tiles get the 2% check too.

Do not trust a guess — use the polythene test or a meter. Saving a week on the covering can cost you the whole floor.